Power supply, equipment testing to determine March 2027 soft opening

TACLOBAN CITY – Completion of power supply requirements and testing of airport equipment will determine whether the upgraded Daniel Z. Romualdez (DZR) Airport, this city, can begin partial operations in March 2027, a public works official said.
Department of Public Works and Highways (DPWH) Eastern Visayas Assistant Regional Director Ma. Margarita Junia said March 2027 is the earliest possible date for the airport’s soft opening, although the schedule remains tentative.
Junia said the project is coordinating with the Leyte Electric Cooperative (Leyeco)II to secure the power supply needed to operate the airport’s expanded facilities and newly installed equipment.
Once electricity requirements are met, the project will proceed with the commissioning of equipment, operational testing, dry runs, and other preparations before the facility can accommodate passengers.
The airport modernization is part of the government’s effort to transform Tacloban’s airport into an international gateway by 2028, improving air connectivity and supporting tourism and economic activities in Eastern Visayas.
Under the development project, the new passenger terminal building will have a floor area of 33,498 square meters, nearly 10 times larger than the existing 3,447-square-meter terminal.
The expanded facility is designed to accommodate 990 passengers for domestic flights and 610 for international flights. It will also have 22 check-in counters, compared with the current three.
Other major improvements include the extension of the runway from 2,142 meters to 2,500 meters and the expansion of the aircraft apron from three to five bays.
The development plan also provides for a 3,000-square-meter cargo terminal, a nine-storey air traffic control tower, and a 14,500-square-meter vehicle parking area that can accommodate 302 vehicles. The airport fire station will also be expanded to 1,100 square meters.
Located in Barangay 88 in the San Jose district, the DZR Airport serves as the principal air gateway to Eastern Visayas, connecting the region to major destinations, particularly Manila and Cebu.
The need to expand the airport has become more pressing with the steady volume of air travelers. In 2024, it recorded approximately 1.69 million passengers and handled an average of 24 flights daily.
Once completed, the modernization is expected to improve passenger capacity and travel convenience while strengthening the region’s access to domestic and international markets.
However, Junia emphasized that the March 2027 target is not yet final, as actual operations will depend on the completion of essential utilities and the successful testing of airport systems.